St. Gall Battery Energy Storage System

Energy Vault’s B-VAULT™ AC battery energy storage system (BESS) shifts regional wind and solar generation, stabilizing the Texas grid while increasing customer revenue.

Project Overview

Located near Fort Stockton in Pecos County, Texas, the St. Gall Battery Energy Storage System (BESS) is a 100 MW-ac / 200 MWh-ac project utilizing 76 of Energy Vault’s fully integrated B-VAULT™ AC battery containers (First generation, 2.76 MWh-ac per container)

The project operates within the Energy Reliability Council of Texas (ERCOT) energy and ancillary services markets, generating merchant revenue by providing energy shifting and reliability services to the Texas grid.

At the St. Gall site, Energy Vault delivered comprehensive Engineering, Procurement, and Construction (EPC) wrap services. Leveraging its extensive commissioning and start-up (CSU) expertise and the B-VAULT's user-friendly system architecture, Energy Vault successfully commissioned the 200 MWh-ac St. Gall project in a record time of just 14 days.

During operation, Energy Vault’s proprietary EMS software, VaultOS, monitors and controls all aspects of the BESS, from daily operations to advanced market bidding and system maintenance. While undergoing testing, the St. Gall system surpassed ERCOT's 250ms maximum requirement for Fast Frequency Response (FFR).

icon_checks
Customer: Jupiter Power
icon_checks
Location: Fort Stockton, Pecos County, Texas
icon_checks
Products: B-VAULT™ AC, VaultOS™
icon_checks
Peak Power Output: 100 MW AC
icon_checks
Energy: 200 MWh AC
icon_checks
Project Status: Operating
icon_checks
COD: March 2024

St. Gall Battery Energy Storage System

St. Gall Project Highlights

Easy to Find
Easy to Run

VaultOS™ will make it easy for the customer to operate its battery assets, with advanced analytics and an EMS user interface designed for people.

Project Management
Innovative Design

The B-VAULT™ AC integrates all batteries, PCS, and Balance of Plant (BoP) functionalities for streamlined operations.

ficn6
Lightning Fast Response Time

The St. Gall system boasts a 180ms response time enabled by VaultOS™ and B-VAULT™ making Energy Vault's system capable of meeting response time requirements domestically and abroad.

Registry Editor
Flexible Operations

The project’s future-proofed hardware and software architecture ensures that the St. Gall BESS will be able to provide a variety of grid services, both now and as the grid evolves.

Title

Lorem ipsum dolor sit amet, consectetur adipiscing elit, sed do eiusmod tempor incididunt ut labore et dolore magna aliqua. Ut enim ad minim veniam, quis nostrud exercitation ullamco laboris nisi ut aliquip ex ea commodo consequat.

Name Surname

Position, Some Company

Title

Lorem ipsum dolor sit amet, consectetur adipiscing elit, sed do eiusmod tempor incididunt ut labore et dolore magna aliqua. Ut enim ad minim veniam, quis nostrud exercitation ullamco laboris nisi ut aliquip ex ea commodo consequat.

Name Surname

Position, Some Company

Title

Lorem ipsum dolor sit amet, consectetur adipiscing elit, sed do eiusmod tempor incididunt ut labore et dolore magna aliqua. Ut enim ad minim veniam, quis nostrud exercitation ullamco laboris nisi ut aliquip ex ea commodo consequat.

Name Surname

Position, Some Company

Title

Lorem ipsum dolor sit amet, consectetur adipiscing elit, sed do eiusmod tempor incididunt ut labore et dolore magna aliqua. Ut enim ad minim veniam, quis nostrud exercitation ullamco laboris nisi ut aliquip ex ea commodo consequat.

Name Surname

Position, Some Company

Title

Lorem ipsum dolor sit amet, consectetur adipiscing elit, sed do eiusmod tempor incididunt ut labore et dolore magna aliqua. Ut enim ad minim veniam, quis nostrud exercitation ullamco laboris nisi ut aliquip ex ea commodo consequat.

Name Surname

Position, Some Company

In more news

A small description up and coming news articles.

"The Energy Vault team’s deep expertise and collaborative approach were critical to the rapid design and commissioning of this unique, AC-coupled BESS configuration."

Michael Geier

Chief Technology Officer, Jupiter Power